Accelerated EPC Project Sequence
Benefits
- Shortest project schedule
- Lowest engineering costs
- One company responsible for all phases, turnkey
- Requires lowest degree of client project management staff and infrastructure
- Highest degree of coordination (communication) between phases
Drawbacks
- Client commits to cost and schedule based on estimates within a 25 to 40% range of accuracy
- Higher risk for changes as project develops (reflected in the estimates with lower range of accuracy)
Application
- Projects requiring shorter schedules: profit generating projects
- Common projects with standard scopes of work, reduced risks of unknowns
|
Traditional Project Sequence
Benefits
- Least expensive construction costs
- Phases of the project can be competitively bid
- Estimates are available on cost and schedule at each phase before client commitment to the next phase. Estimate accuracy improves from conceptual to 40%, 10% and finally “definitive” as phases are completed
- Lower risk for changes as project develops
Drawbacks
- Longest project schedule
- Highest engineering costs
- Requires highest degree of client project management staff and infrastructure
- Requires coordination between companies
Application
- Projects without schedule pressure (i.e., non-profit projects)
- Projects with complex scopes of work
- Unique or uncommon projects which have a higher degree of unknowns, risk
|